|
|
|
|
|
|
|
The exterior of Long Island Railroad commuter coach prior to beginning conversion work on February 7, 2004. |
|
|
|
|
|
|
|
|
|
|
|
|
Interior of Long Island commuter coach prior to beginning of rebuild project. |
|
|
|
|
|
|
|
|
|
|
|
|
First project was the removal of the seat cushions and luggage racks. |
|
|
|
|
|
|
|
|
|
|
|
|
Next came the removal of the seat frames and old plastic light fixtures. |
|
|
|
|
|
|
|
|
|
|
|
|
Next to be removed was the center air grilles from the ceiling down the middle of the car. |
|
|
|
|
|
|
|
|
|
|
|
|
Now the ceiling is ready to be cleaned, sanded and then repainted. Eventually new wood ceiling panels will be fabricated and installed. |
|
|
|
|
|
|
|
|
|
|
|
|
Then the aluminum interior trim around the windows was removed. |
|
|
|
|
|
|
|
|
|
|
|
|
Next to come down was the aluminum upper wall panels. This required alot of grinding of old fasteners. |
|
|
|
|
|
|
|
|
|
|
|
|
Next to be removed was the stainless steel lower wall panels and the aluminum window frames with very scratched lexan windows. |
|
|
|
|
|
|
|
|
|
|
|
|
Next came the removal of the old restroom. |
|
|
|
|
|
|
|
|
|
|
|
|
Then the old electrical strip heaters were removed and the old, mostly wet insulation was removed. |
|
|
|
|
|
|
|
|
|
|
|
|
This is what the completely stripped interior looked like on March 4, 2004. |
|
|
|
|
|
|
|
|
|
|
|
|
Exterior work began in mid-March and continued into April. Dozens of side sheet patches were required on each side of chapel car. |
|
|
|
|
|
|
|
|
|
|
|
|
Close-up of window openings being made smaller on alter end of the car. Eventually these windows will have side facing stained glass. |
|
|
|
|
|
|
|
|
|
|
|
|
During this time new support members needed to be welded in above the window openings. |
|
|
|
|
|
|
|
|
|
|
|
|
In mid-April the first of the cut down pews were brought for a test fit. The left side will have 3 person seating and the right will have 2 person. |
|
|
|
|
|
|
|
|
|
|
|
|
The fun really began with only 18 days to go before the wedding. We had a countdown sign on the wall and took pictures of each days progress. |
|
|
|
|
|
|
|
|
|
|
|
|
The new window frames were being built in the tool car. |
|
|
|
|
|
|
|
|
|
|
|
|
Extensive concrete repairs were necessary as the support structure under the bathroom rotted away. |
|
|
|
|
|
|
|
|
|
|
|
|
A casket door was added to the side of the car adjacent to the alter to allow for funerals. |
|
|
|
|
|
|
|
|
|
|
|
|
Exterior view of new door. |
|
|
|
|
|
|
|
|
|
|
|
|
On May 19, 2004 the exterior finally got its' coat of Pullman Green paint. |
|
|
|
|
|
|
|
|
|
|
|
|
The new concrete was poured in the floor. |
|
|
|
|
|
|
|
|
|
|
|
|
And the new glass arrived for the side windows. |
|
|
|
|
|
|
|
|
|
|
|
|
May 20, 2004 found additional painting done and the first of the new windows installed. |
|
|
|
|
|
|
|
|
|
|
|
|
Several additional bad spots were repaired in the floor. |
|
|
|
|
|
|
|
|
|
|
|
|
May 22, 2004 found the installation of the rest of the new windows and the beginning of the new electrical wiring. |
|
|
|
|
|
|
|
|
|
|
|
|
May 24th saw installation of additional conduit. |
|
|
|
|
|
|
|
|
|
|
|
|
The new ceiling installation began on May 26th. |
|
|
|
|
|
|
|
|
|
|
|
|
The new plywood underlayment was installed with a great deal of difficulty. |
|
|
|
|
|
|
|
|
|
|
|
|
May 26th also shows the walls ready for new insulation. |
|
|
|
|
|
|
|
|
|
|
|
|
May 28 shows the completion of the insulation and the installation of the new wall below the windows. |
|
|
|
|
|
|
|
|
|
|
|
|
Time is getting very short with the wedding now only 8 days away. |
|
|
|
|
|
|
|
|
|
|
|
|
A new circuit breaker panel was installed. |
|
|
|
|
|
|
|
|
|
|
|
|
New wire was finally pulled through the new conduit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
New ceiling light fixtures were installed. |
|
|
|
|
|
|
|
|
|
|
|
|
New red oak wall paneling was installed above and between windows. |
|
|
|
|
|
|
|
|
|
|
|
|
Good wide view of progress with only one week to go. |
|
|
|
|
|
|
|
|
|
|
|
|
Time is growing very short. Time for the second shift to begin work. |
|
|
|
|
|
|
|
|
|
|
|
|
The alter wall is built. Hole will accommodate the large stained glass window. |
|
|
|
|
|
|
|
|
|
|
|
|
View down the new hallway behind the alter. |
|
|
|
|
|
|
|
|
|
|
|
|
New oak door is installed to create closet at end of the hall. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mardell gives pews a final sanding. |
|
|
|
|
|
|
|
|
|
|
|
|
Al puts together alter wall and installs doors to clergy preparation room and passageway to next car. |
|
|
|
|
|
|
|
|
|
|
|
|
Josh works to shorten communion railing for front of chapel. |
|
|
|
|
|
|
|
|
|
|
|
|
The various pieces of furniture are brought in to check spacing. This is the first opportunity to see what the chapel will look like. |
|
|
|
|
|
|
|
|
|
|
|
|
Only four days remain and the pews finally get stained. The weather was not complimentary to this type of work. |
|
|
|
|
|
|
|
|
|
|
|
|
Various pieces of trim get a couple of coats of varnish. |
|
|
|
|
|
|
|
|
|
|
|
|
Walls get their first coat of varnish. |
|
|
|
|
|
|
|
|
|
|
|
|
Extended family begins to arrive for the big day! |
|
|
|
|
|
|
|
|
|
|
|
|
Audio/Video control room is constructed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Breanna paints the lower walls and pew supports. |
|
|
|
|
|
|
|
|
|
|
|
|
Spot lights are installed above alter. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Car is definately coming together but will it all get done in time. |
|
|
|
|
|
|
|
|
|
|
|
|
Lettering is applied to exterior of the car. Now everyone in town knows what the project is about. |
|
|
|
|
|
|
|
|
|
|
|
|
Stained glass is installed. |
|
|
|
|
|
|
|
|
|
|
|
|
Audio system is installed and works. Now we can have some motivational music for the race to completion. |
|
|
|
|
|
|
|
|
|
|
|
|
Early in the evening the first pews are brought in from the farm. |
|
|
|
|
|
|
|
|
|
|
|
|
Crew worked until 4 am to get the carpet and pews in place. |
|
|
|
|
|
|
|
|
|
|
|
|
View of car at 6 am on wedding day. Atleast the guests will have a place to sit. |
|
|
|
|
|
|
|
|
|
|
|
|
Alter area still needs a bit of work on Saturday morning. |
|
|
|
|
|
|
|
|
|
|
|
|
Almost unbelievably the ceremony took place on time at 4:15 pm on June 5, 2004. Greg thanks everyone for their assistance and welcomes the guests. |
|
|
|
|
|
|
|
|